Difference between revisions of "Project Management"
(Created page with "Noolaham Foundation has adopted an integrated approach to project development and management. Projects are broadly classified as Program related and Operations related. All...") |
|||
(One intermediate revision by the same user not shown) | |||
Line 4: | Line 4: | ||
== Project Life Cycle == | == Project Life Cycle == | ||
− | {{Project Life Cycle}} | + | {{ :Project Life Cycle }} |
Latest revision as of 04:09, 18 July 2020
Noolaham Foundation has adopted an integrated approach to project development and management. Projects are broadly classified as Program related and Operations related. All Program projects are carried out by an integrated team of staff and volunteers across geographic offices and Chapters as appropriate. Chapters are able to undertake resource mobilization and outreach related activities on their own, but not program related activities. This arrangement is needed to ensure to avoid duplication and bring an integrated focus to the Noolaham Foundation program. All of Noolaham Foundation projects must be towards achieving its mission and objectives and in accordance with its guiding principles, strategy, policies and standards. Even if external funding is not available, Noolaham Foundation has a duty to balance underrepresented voices and communities in its projects. A participatory and collaborative approach is used at all stages of the projects with all stakeholders. All project activities undertaken by volunteers and staff from the initial stages must be done transparently. Specifically, if volunteers or staff outreach potential collaborators or vice versa, she/he must inform via the Initiatives & Proposal Writing thread regarding the interaction.
Project Life Cycle
- Noolaham Foundation and relevant volunteers or stakeholders identify a project.
- Noolaham Foundation prepares a proposal document (Annex 5) which consists of Background and objectives, Target and Results, Justification, Beneficiaries, * Implementations, Budget, Work plan, and required annexure.
- The proposal is forwarded to management for assessment and approval by the Program Officer.
- The proposal is then submitted to the Governance Board for review and approval.
- If donors agree, an agreement should be signed between the Noolaham Foundation and donor agency.
- A more detailed Project Management Plan must be developed by the Program Officer extending the proposal. This plan must be approved by the Chief Operating Officer.
- As a general rule, Noolaham Foundation will do the procurement for projects. If any exceptions are to be made, the implementing agency should consult the Operations Unit in Noolaham Head Office.
- Funds shall be released to the implementing agency or obtained from donor agency as per agreement and against the milestones and deliverables. Generally, minimum 50% of the funds should be released before the project can commence.
- Project Status Updates must be submitted weekly to the Program Manager. Project Update Report must be submitted monthly on an agreed upon frequency by the Chief Operating Officer to the relevant stakeholders.
- After the close of the project, a Project Post-Mortem meeting should be held within one month with all stakeholders. The Lessons Learned and/or Learning Patterns should be documented in the Final Project Report.
- The Final Project Report must be submitted and approved by the Governance Board within three months.